Bid Package 1- (Awarded March 27, 2006)
Multi-Campus Turf Installation
Milestone Dates:
· Substantial Completion was January 22, 2007
Bid Package 2 - (Awarded May 15, 2006)
Bear Creek ES Addition & Renovations
Milestone Dates:
· Additions completed January 3, 2007
· Completed August 16, 2007
Colleyville Heritage High School Parking Lot Addition
Milestone Dates:
· Substantial completion on September 11, 2006
Cross Timbers MS Addition & Renovations
Milestone Dates:
· Additions began December 5, 2006 and scheduled completion on September 20, 2007
· Renovations begin May 31, 2007and scheduled completion on July 3, 2007
Mustang/Panther Stadium & Fieldhouse Addition & Renovations
Milestone Dates:
· Restroom Additions began December 7, 2006 to April 10, 2007
· Fieldhouse Renovations began December 1, 2006 and scheduled completion on April 10, 2007
· Ticketbooth and Stadium Renovations began January 11, 2007and scheduled
completion on April 25, 2007
Timberline ES Addition & Renovations
Milestone Dates:
· Parking Additions began July 6, 2006 and completed on August 15, 2006
· Library Additions began July 26, 2006 and scheduled completion on March 19, 2007
· Enrichment Center Renovations began July 30, 2006 and completed on 12/7/06
· Interior Renovations begin May 31, 2007 and scheduled completion on August 13, 2007
Bid Package 3- (Awarded June 19, 2006)
Colleyville MS Addition & Renovations
Milestone Dates:
· New Gymnasium Additions began July 15, 2006 and scheduled completion on
March 10, 2007
· Renovations begin May 31, 2007 and scheduled completion on August 15, 2007
New Colleyville Elementary School
Milestone Dates:
· Construction began June 31, 2006 and scheduled completion on July 31, 2007
Bid Package 4 - (Awarded June 19, 2006)
Heritage MS Addition & Renovations
Milestone Dates:
· Additions began September 15, 2006 and scheduled completion on June 15, 2007
· Renovations begins May 31, 2007 and scheduled completion on August 14, 2007
Silver Lake ES Additions & Renovations
Milestone Dates:
· Additions began August 7, 2006 and scheduled completion on April 19, 2007
· Renovations began May 31, 2007 and scheduled completion on July 31, 2007