Bid Package 5 (Awarded March 26, 2007)
Bransford Elementary School Renovations
Milestone Dates:
· Renovations began May 29, 2007 and scheduled completion is August 31, 2007
Colleyville Heritage High School Additions & Renovations
Milestone Dates:
· Phase I - Renovations began May 29, 2007 and scheduled completion is August 31, 2007
· Phase II - Renovations begin June 5, 2008 and scheduled completion is August 30, 2008
· Additions began May 29, 2007 and completion November 19, 2007
Existing Colleyville Elementary
(Professional Development & Education Center) Renovations
Milestone Dates:
· Renovations began September 1, 2007 and scheduled completion is June 30, 2008
Glenhope Elementary School Renovations
Milestone Dates:
· Renovations began May 29, 2007 and scheduled completion August 31, 2007
Grapevine High School Addition & Renovations
Milestone Dates:
· Phase I- Renovations began May 29, 2007 and completion August 31, 2007
· Phase II- Renovation begin June 5, 2008 and scheduled completion August 30, 2008
O.C Taylor Elementary School Addition & Renovations
Milestone Dates:
· Additions began May 29, 2007 and scheduled completion August 31, 2007
· Renovations began May 29, 2007 and scheduled completion August 31, 2007
Bid Package 6
Administration Building Renovations
Project placed on “HOLD” until further notice.
Cannon Elementary School Renovations
Milestone Dates:
· Renovations to begin June 5, 2008 and scheduled completion August 11, 2008
Dove Elementary School Renovations
Milestone Dates:
· Renovations to begin June 5, 2008 and scheduled completion August 11, 2008
Facility Services & Finance Building Renovations
Project placed on “HOLD” until further notice.
Grapevine Elementary School Renovations
Milestone Dates:
· Renovations to begin June 5, 2008 and scheduled completion August 11, 2008
Grapevine Middle School Renovations
Milestone Dates:
· Renovations to begin June 5, 2008 and scheduled completion August 11, 2008
Heritage Elementary School Renovations
Milestone Dates:
· Renovations to begin June 5, 2008 and scheduled completion August 11, 2008
Instructional Support Center Renovations
Milestone Dates:
· Renovations began July 12, 2007 and completion January 3, 2008
Swim Center Renovations
Milestone Dates:
· Renovation to begin May 28, 2008 and scheduled completion August 05, 2008
Tax Office Renovations
Project placed on “HOLD” until further notice.
Transportation Building Renovations
Project placed on “HOLD” until further notice.
Warehouse Building Renovations
Project placed on “HOLD” until further notice.
|