| 08/25/08 |
The GCISD Board of Trustees heard an update on activities related to the 2005 Bond Program during the regular meeting on August 25, 2008. The following update was presented:
- On Bid Package 5, work is complete at the Professional Development and Education Center (former CES and both high schools, and all facilities were ready for students to arrive for the first day of school. Contractors will continue working through punch list items.
- On Bid Package 6, renovations to Cannon, Dove, Grapevine and Heritage elementary schools, Grapevine Middle School and the Swim Center are complete. However, the new floor coverings in the corridors at Grapevine Elementary had imperfections and will be replaced this school year (during a student holiday yet to be determined). All facilities were ready for students to arrive for the first day of school. Contractors will continue working through punch list items.
- On Bid Package 7, planning continues for the six-classroom addition to Cannon Elementary and renovations to the Transportation Services, Facility Services and Tax Office facilities. The Board previously approved Competitive Sealed Proposal as the construction delivery method for this package. Proposals will be opened beginning September 4, 2008, and a recommendation for a general contractor will be presented to the Board on September 22, 2008. Construction is scheduled to begin October 1, 2008, with substantial completion expected July 15, 2009.
|
| 07/21/08 |
An update on activities related to the 2005 Bond Program was presented during the GCISD Board of Trustees meeting on July 21, 2008. Progress reported included:
-
On Bid Package 5, work is nearly complete at the Professional Development and Education Center (former CES). The Bridges and Vista alternative education programs as well as the Nutrition Services, Special Services and Staff Development departments are scheduled to begin moving into their office spaces on July 25. Phase II of renovations is underway at Colleyville Heritage and Grapevine high schools. At CHHS, painting and floor covering installations in the classrooms on the second and third floors are complete, ceramic tile installation throughout the building is nearly complete, and painting continues in the athletic areas. At GHS, renovations in the 700 hallway are complete and furniture is being re-installed. Carpet installation is in progress in the main corridors, new ceilings and floor coverings are being installed in the band hall, millwork continues in classrooms and the main office, and installation of new doors and hardware continues. Interior painting is in progress throughout the building while exterior painting is nearly complete. Renovations at both high schools are scheduled to be complete by early August.
- On Bid Package 6, renovations to Cannon, Dove, Grapevine and Heritage elementary schools, and Grapevine Middle School, is in progress. Work includes removal and replacement of carpet/floor coverings, wall coverings, roofing, HVAC equipment and electrical systems. At the Swim Center, installation of HVAC equipment is complete and new pool filters are operational. New lighting for the pool area is being installed, interior painting is in progress and roofing is near completion.
- On Bid Package 7, planning has begun for the six-classroom addition to Cannon Elementary and renovations to the Transportation Services, Facility Services and Tax Office facilities. The Board previously approved Competitive Sealed Proposal as the construction delivery method for this package. Proposals will be opened beginning September 4, 2008, and a recommendation for a general contractor will be presented to the Board on September 22, 2008. Construction is tentatively scheduled to begin October 1, 2008, with substantial completion expected July 15, 2009.
|
| 06/16/08 |
An update on activities related to the 2005 Bond Program was presented during the GCISD Board of Trustees meeting on June 16, 2008. Progress reported included:
-
On Bid Package 5, work continues at the Professional Development and Education Center (former CES). Installation of ceiling tiles, carpet and other floor coverings is progressing and interior painting continues throughout the building. The cafeteria floor is being repaired in preparation for tile installation, and existing millwork is being removed for new cabinet installation. Phase II of construction at Colleyville Heritage and Grapevine high schools has begun. At CHHS, carpet, vinyl wall covering and acoustical ceilings are being removed; removal and replacement of roofing is progressing and HVAC installation has begun. At GHS, carpet is being removed; existing millwork is being removed and replaced; and exterior painting is progressing.
On Bid Package 6, renovations to Cannon, Dove, Grapevine and Heritage elementary schools, and Grapevine Middle School, began June 11. Work includes removal and replacement of carpet/floor coverings, wall coverings, roofing, HVAC equipment and electrical systems. Interior and exterior painting is progressing. At the Swim Center, installation continues on ceramic tile in the restroom and locker room areas, HVAC equipment and a fire sprinkler system in the pool area. Interior painting and re-roofing also is progressing.
|
| 05/28/08 |
The GCISD Board of Trustees heard an update on activities related to the 2005 Bond Program during the regular Board meeting May 28, 2008. The following information was reported:
-
On Bid Package 5, renovations and additions to Bransford, O.C. Taylor and Glenhope elementary schools were completed during summer 2007. Phase II of construction at Colleyville Heritage and Grapevine high schools will begin in summer 2008, with the majority of work consisting of new carpet, ceramic wall tile and painting. Work is progressing at the Professional Development and Education Center (former CES). The exterior walkway canopy is complete and work is near completion on interior HVAC systems, roofing and sheet metal installation, and electrical systems. Interior painting continues throughout the building and the new parking lot is in progress. New carpet is scheduled to be delivered in early June and installation will begin immediately.
-
On Bid Package 6, renovations and additions to Cannon, Dove, Grapevine and Heritage elementary schools, and Grapevine Middle, will begin June 11. Completion is scheduled for the first week of August 2008.
|
| 04/28/08 |
During the April 28 regular Board of Trustees meeting, an update was provided on current activities related to the 2005 Bond Program:
- On Bid Package 5, ceilings are being installed and carpet installation has begun in the Bridges area at the Professional Development and Education Center (former CES). Interior painting continues throughout the building and installation of HVAC grilles and lighting fixtures is ongoing. Progress is being made on the parking lot excavation and grading.
- On Bid Package 6, construction work on projects in this package is set to begin in June and to be completed before school begins in August.
|
| 04/01/08 |
An update was provided on activities related to the 2005 Bond Program during the GCISD Board of Trustees regular meeting on March 31. The following activities were reported:
- On Bid Package 5, installation continues on new HVAC and electrical systems, new ceiling grid, and millwork and woodwork at the Professional Development and Education Center (former CES). New partitions and drywall installation is complete, as is the parking lot excavation. Interior painting continues.
- On Bid Package 6, Trustees approved the Guaranteed Maximum Price for this package earlier in the meeting. This includes renovations to Cannon Elementary, Dove Elementary, Grapevine Elementary, Heritage Elementary, Grapevine Middle, Colleyville Heritage High School, Grapevine High School and the Swim Center. Construction work on projects in this package is set to begin in June and be completed before school begins in August.
|
| 12/10/07 |
An update on the progress of projects in Bid Packages two, five and six was provided during the GCISD Board of Trustees regular meeting on Dec. 10. The following activities were reported:
- On Bid Package 2, layout of an additional drive at CTMS is complete and excavation is progressing. This will help alleviate traffic congestion at CTMS.
- On Bid Package 5, interior painting has begun at the Professional Development and Education Center (former CES). HVAC ducts are being installed and work continues on roofing, plumbing and electrical. At CHHS, the wrestling and choir additions are complete and in use. Work will continue at both CHHS and GHS in summer 2008.
- On Bid Package 6, installation continues on ceramic tile, electrical systems and ceilings at the Instructional Service Center (ISC). Exterior concrete, parking lot striping and irrigation system is complete, and landscaping, plumbing and HVAC work is in progress. Renovations to the ISC are expected to be complete in the next week. In addition, plans are in progress for renovations to facilities that will be under construction beginning summer 2008.
|
| 10/29/07 |
An update was provided on activities related to the 2005 Bond Program. A video in the ongoing student bond video series was shown highlighting summer construction work at both high school campuses.
- Bid Package-5: (BES, PDEC, GHES, OCTES, CHHS, & GHS)
- On Bid Package 5, demolition is nearing completion at the Professional Development and Education Center (the former Colleyville Elementary), roof replacement is ongoing and new HVAC ducts are being installed. Renovations to the PDEC are expected to be complete in December 2007. At CHHS, painting continues and ceramic tile is being installed on the new choir room, and ductwork is complete in the wrestling room. Both additions are tentatively scheduled to be turned over to the District next week. Exterior site work is progressing as scheduled, and work will continue at both CHHS and GHS in summer 2008.
- Bid Package-6:
- On Bid Package 6, utilities are in place and interior HVAC ducts are being installed at the Instructional Service Center (ISC). Drywall partitions are in place and work continues on electrical and plumbing. Renovations are expected to be complete in December 2007.
|
| 8/27/07 |
All projects that were scheduled to be open for the first day of school were complete by the time students arrived. Exterior site work such as landscaping and irrigation continues on several facilities.
- Bid Package-3: (CMS & New CES)
- Interior finish work continues in the athletic areas at CMS. Parking lot repairs at the tennis courts are in progress, work continues on a canopy walkway and installation of additional exterior lighting has begun.
- Bid Package-4: (SLES & HMS)
- The addition at HMS is complete. Exterior site work at SLES is near completion.
- Bid Package-5: (BES, PDEC, GHES, OCTES, CHHS, & GHS)
- Work continues on the choir and wrestling room additions at CHHS while first-floor interior finishes are complete. At GHS, final detail on interior painting and floor coverings is near completion and adjustments are being made to equipment. Work will continue at both CHHS and GHS in summer 2008. Renovations to the Instructional Service Center (ISC) are expected to be complete in December 2007.
|
| 7/30/07 |
- Bid Package-1: (MCFI – Multi-Campus Field Improvements)
- All projects are complete.
- Bid Package-2: (BCES, CTMS, M/P Stadium, TES, CHHS Parking Lot)
-
Work at BCES, CTMS and TES is in the final stages and is scheduled to be complete in August. Construction on the new parking lot at CTMS continues as does exterior site work, landscaping and irrigation.
- Bid Package-3: (CMS & New CES)
-
At the new CES, interior work is complete and final details are being completed. Furniture is being moved into classrooms. Landscape installation begins this week, as site grading and irrigation is already in progress. GCISD has completed its work on Pleasant Run Road and the City of Colleyville is working on its portion of the road. At CMS, interior finishing work continues while exterior masonry continues on the gym extension. The gym floor is being installed. Progress continues on the new w eight room and fine arts wing. Both CES and CMS are scheduled to be complete in August.
- Bid Package-4: (SLES & HMS)
-
The addition at HMS is nearing completion, interior finishing work is in progress in the renovated areas, flooring is being installed in the science addition and exterior site grading continues. At SLES, interior work is complete and furniture is being installed. Exterior site work and landscaping is in progress.
- Bid Package-5: (BES, PDEC, GHES, OCTES, CHHS, & GHS)
-
Interior work continues in the corridors and classrooms at OC Taylor. Kitchen renovation is on-going and all new equipment is on site. At BES, interior work is near completion and furniture is being installed. Re-roofing continues and is scheduled to be complete this week. At GHES, exterior site work and cleanup continues. At CHHS, furniture is being installed in the classrooms and the floor slab has been poured for the choir room addition. The gym floor at GHS is in the finishing process, ceramic tile is being installed in the kitchen and interior finishing work continues throughout. Exterior masonry work continues at the loading dock and new cooler/freezer location, site paving is ongoing and roofing work continues. Renovations on the PDEC are scheduled to begin in September.
|
| 6/18/07 |
- Bid Package-1: (MCFI – Multi-Campus Field Improvements)
- All projects are complete.
- Bid Package-2: (BCES, CTMS, M/P Stadium, TES, CHHS Parking Lot )
-
Work at BCES and CTMS is progressing and is scheduled to be complete in August. The new library addition and conversion of the former Enrichment Center at Timberline Elementary is complete, and painting and tile installation continues. At Mustang-Panther Stadium, the restroom/ticket booth is complete.
- Bid Package-3: (CMS & New CES)
-
At the new CES, exterior site work is
in progress and roofing is 95 percent complete. Interior work including painting, tile installation, plumbing and electrical continues. Drainage work at Pleasant Run Road is near completion and road work will follow as weather permits. At CMS, millwork is being installed and exterior wall work continues on the Brown Gym. HVAC and electrical work is underway and walls are being prepped for painting.
- Bid Package-4: (SLES & HMS)
-
The addition at HMS is scheduled to be complete during the fall semester. New ceilings are being installed in the addition and ductwork and electrical overhead is being finalized. Science casework is in place and final hook-ups are being performed. At SLES, new wall finishes are being completed, new ductwork is being installed and HVAC/electrical work is ongoing. Exterior painting is underway.
- Bid Package-5: (BES, PDEC, GHES, OCTES, CHHS, & GHS)
-
Interior renovations are underway at BES and GHES. HVAC, electrical and plumbing work continues at OC Taylor. Major roofing operations have begun at GHS as well as
kitchen renovation, painting and parking lot overlay work. At CHHS, progress on the new choir and wrestling room addition has slowed due to weather, but interior painting, tile installation and HVAC/electrical work continues.
|
| 5/21/07 |
- Bid Package-1: (MCFI – Multi-Campus Field Improvements)
- Bid Package-2: (BCES, CTMS, M/P Stadium, TES, CHHS Parking Lot )
- Cross Timbers Middle – (August Completion)
- Exterior masonry continues - gym walls are complete and walls at restroom area are in process
- HVAC and electrical installation is progressing in the gym area
- Roofing installation continues - building is in the dry
- Timberline Elementary
- Addition is complete and punch lists are progressing
- Shelving has been moved from existing library
- M/P Stadium Field house – (March Completion**)
- Mustang field house is complete and punch lists have been made
- Restroom and ticket booth is near completion with concrete work remaining to be completed
- Bid Package-3: (CMS & New CES)
- Colleyville Middle – New Gymnasium
- New gymnasium is completed
- Demolition of the exterior wall at the existing gym is complete
- Removal of the existing gym floor is complete
- Pier drilling is to begin when school is out
New Colleyville Elementary
- Masonry is complete and cleaning is in process
- Roofing continues - building is in the dry
- Windows and storefronts are being installed
- Kitchen equipment is being installed
- Ceramic tile in the corridors continues
- Quarry tile is installed in the kitchen and is beginning in the vestibules
- Overhead inspection was conducted with R.R. & B on Friday
- Ceiling grids are in place
- Interior painting continues throughtout the building
- Exterior site work is beginning and front parking lot is in progress
- The added drainage at Pleasant Run is to begin next week and road work will start as soon as the drainage is complete
- HVAC and electrical continues with installation of equipment and final connections
- Bid Package-4: (SLES & HMS)
- Heritage Middle – (Fall Semester 07)
- Masonry is complete and cleaning is in process
- Interior wall painting is on going
- Ceiling grids are being installed in classrooms
- Science equipment is on site and installation will begin on Monday
- HVAC and electrical is progressing throughout the building
- Roofing continues and building is in dry
- Exterior site work has begun and sidewalks are being installed
- Silverlake Elementary – (April 07)
- The classroom addition is near completion and punch lists have been made
- Exterior site work is in progress
- Bid Package-5: (BES, PDEC, GHES, OCTES, CHHS, & GHS)
- O.C. Taylor
- Roof top units to be removed on 5/08/2007
- Roofing material to be staged prior to school release date
- Restroom adddition to begin on 5/25/2007
- Colleyville Heritage High
- Pier steel is currently being tied for Wrestling Addition
- Pier drilling to begin on 5/07/2007
- Soil density testing in progress for Choir Addition
- Gym #2 is currently being painted
- The Dance Gym painting is complete
- Grapevine High
- Hunt relocation existing freezer condensing unit to roof
- Pier drilling to begin next week at loading dock
- Hunt is currently identifying underground utilities at loading dock area
|
| 3/26/07 |
- Bid Package-1: (MCFI – Multi-Campus Field Improvements)
- Bid Package-2: (BCES, CTMS, M/P Stadium, TES, CHHS Parking Lot )
- Cross Timbers Middle – (August Completion)
- Floor slab is complete for the new gymnasium.
- Structural steel columns and joists are now in place.
- Roof deck is currently being installed in the gym area.
- Under-floor plumbing and mechanical items are complete.
- CMU installation is scheduled to begin 1st week in April.
- Timberline Elementary
- New Library Addition is nearing completion and relocation of furniture is scheduled for early May.
- M/P Stadium Field house – (March Completion**)
- CMU wall work is complete on the restroom / South Ticket Booth.
- Roof framing is in progress at the restroom / Ticket Booth.
- All seats and benches are complete at the Stadium Home Side.
- Interior work at the Field House and Dressing Room is nearing completion.
- All new lockers are in place in the Field House.
- All work at the Field House scheduled to complete in two weeks.
- Bid Package-3: (CMS & New CES)
- New Colleyville Elementary
- Exterior masonry continues and is approximately 85% complete.
- Interior drywall partitions are near completion.
- Texture and painting of interior walls now in progress.
- Overhead low-voltage wiring is being installed.
- Millwork is now fabricated and ready for installation.
- Colleyville Middle – New Gymnasium
- Exterior windows are now in place.
- Ceramic tile is complete in locker rooms and toilets.
- Gym floor is in place and striping will be installed next week.
- Bleachers are in place and controls are being installed now.
- Basketball backboards are being installed.
- Painting and finish of miscellaneous items continues.
- Exterior canopy in now in place.
- Landscape and irrigation is being installed now.
- Bid Package-4: (SLES & HMS)
- Heritage Middle – (Fall Semester 07)
- Interior masonry walls are nearing completion.
- Awaiting delivery of interior face brick to complete load bearing walls.
- Structural Steel is on site and ready for installation.
- Silverlake Elementary – (April 07)
- All exterior masonry is complete.
- Roofing is nearing completion.
- Interior drywall partitions are complete.
- HVAC ductwork installation is nearing completion.
- Overhead electrical work continues.
- Bid Package-5: (BES, PDEC, GHES, OCTES, CHHS, & GHS)
- Review & Award GMP Tonight!
|
| 2/26/07 |
- Bid Package-1: (MCFI – Multi-Campus Field Improvements)
- Bid Package-2: (BCES, CTMS, M/P Stadium, TES, CHHS Parking Lot )
- Bear Creek Elementary - A few punch list items remain.
- Cross Timbers Middle – (August Completion) All foundation piers will be complete by Thursday 3/1/07.
- Foundation grade beams are being formed and a portion have been poured to date.
- Under floor plumbing rough-in is now in progress.
- New parking lot area is ready for construction, pending ‘work scope’ resolution. (Work order proposal was received on Tuesday from Hunt Construction).
- Timberline Elementary
- Ceiling grids are in place and ready for above-ceiling inspections.
- Demolition of existing walls at the tie-in to the existing building are complete.
- Painting of walls and ceiling bulkheads is in progress. All exterior concrete is complete and exterior grading/irrigation installation is on-going.
- M/P Stadium Field house – (March Completion**)
- New chair-back seating and aluminum planks are complete on the Stadium Home Side.
- New handicap seating areas have been installed and concrete is ready to be installed.
- New lockers for the field house are now installed.
- All CMU replacement wall areas are now ready for finishes and ceramic floor tile.
- Roofing and new exterior downspouts are near completion
- Bid Package-3: (CMS & New CES)
- New Colleyville Elementary
- Exterior masonry wall work continues
- Interior drywall partitions and wall insulation being installed.
- Interior plumbing, electrical and mechanical installations continue.
- Hanging sheetrock on partition walls in all classrooms.
- TB&T has begun in some classrooms.
- Under floor plumbing is nearing completion in the kitchen.
- Roofing and sheet metal work continues.
- Site work continues at the detention pond, irrigation lines being installed.
- Preliminary road work at Pleasant Run has begun.
- Colleyville Middle – New Gymnasium
- Exterior face brick operations nearing completion.
- Roofing and sheet metal work is nearing completion.
- Interior walls of gymnasium have been painted and wall graphics are in place.
- Gym flooring is being installed.
- Ceramic tile is being installed in locker rooms and toilet rooms.
- All gym lighting and electrical overhead work is operational.
- All HVAC work is in place and operational.
- Bid Package-4: (SLES & HMS)
- Heritage Middle – (Fall Semester 07)
- All floor slabs are now complete!
- Exterior CMU walls are now complete!
- Interior masonry walls are being constructed.
- Plumbing and electrical rough-in for CMU walls is on-going.
- Silverlake Elementary – (April 07)
- Exterior brick veneer is being installed and scheduled to be complete by end of the week.
- Structural steel is in place and roof tie-in will begin next week.
- Electrical and mechanical rough-in continues.
- Bid Package-5: (BES, PDEC, GHES, OCTES, CHHS, & GHS) – Received Subcontractor Bids Tuesday 2/20/07.
- Hunt Construction is now scoping all trades and their proposals.
- Excellent Turnout – Over 300 contractors were notified of the project.
- Market is saturated right now – everyone’s extremely busy!
- GMP Meetings to begin 3/12/07.
- GMP to the Board of Trustees – Monday 3/26/07.
|
| 1/22/07 |
- Bid Package 1: (Multi-Campus Field Improvements)
- Football fields (artificial turf) are complete, including punch list items.
- CHHS Baseball Field Update
- Infield grass was placed on Saturday, 1/17/07. Work continues through today, Monday 1/22/07. Concrete halo was constructed and touch-up work will also continue through the week.
- Bid Package 2: (BCES, CTMS, M/P Stadium, TES, CHHS Parking Lot)
- Bear Creek Elementary
- Substantial Completion has been issued, teachers occupy the spaces.
- Punch lists are being worked off by Hunt and should be complete by the first part of February 2007.
- Cross Timber Middle - (August Completion)
- Parking lot layout is complete. Weather has impeded progress somewhat.
- Underground storm drainage system is complete.
- Pier Drilling for foundation to start when weather and ground conditions permit.
- Timberline Elementary
- Exterior window installation is complete at Library addition - (March completion).
- Interior drywall ceilings and walls are near completion.
- Overhead work, electrical, ductwork, technology wiring is now complete.
- M/P Stadium Field house - (March Completion**)
- Re-roof work started in December and is nearing completion.
- Started interior renovation work in weight room & locker rooms.
- Bid Package 3: (CMS & New CES)
- New Colleyville Elementary
- Steel erection is 95% complete. Front entrance is last of the areas to be completed.
- Interior stud partitions are being installed.
- Roofing operation has begun on the project.
- Overhead work, electrical, plumbing, and ductwork is in place throughout the building.
- Exterior masonry veneer work has started.
- Road work on Pleasant Run to start, weather permitting, in the next couple of weeks
- Parking lots and roads are complete on-site.
- Colleyville Middle
- Brick veneer work is now 80%!
- Interior masonry walls are complete.
- Interior painting operations has begun in the gymnasium.
- HVAC ductwork and electrical rough-in is now complete in the gym.
- Bid Package 4: (SLES & HMS)
- Heritage Middle - (Fall Semester 2007)
- Poured one floor slab to date. Remaining floor slab areas to be poured next week, weather permitting.
- Mobilized for constructing CMU walls.
- Exterior utilities are all in place now.
- Silverlake Elementary - (April 2007)
- Exterior walls are now complete, damp proofing operations are in progress.
- Interior overhead electrical, mechanical work is in progress.
- Structural steel is complete and roof decking is near completion.
- Site utility work is nearing completion.
|
|
| 12/11/06 |
- Bid Package-1: (MCFI – Multi-Campus Field Improvements)
- The final topographic survey for the baseball field at CHHS has been completed and is being reviewed by the civil engineer. üThe baseball field at CHHS has been over seeded now.
- Bid Package-2: (BCES, CTMS, M/P Stadium, TES, CHHS Parking Lot )
- Bear Creek Elementary
- Brick veneer has been delivered and is being constructed now.
- Interior finishes are near complete. Flooring to follow.
- All overhead work, HVAC, Electrical, Data, etc. is complete now.
- Ceiling work to start this week.
- Cross Timbers Middle
- Tree protection is in-place.
- New parking lot is laid out and forming work progressing through the next two weeks.
- M/P Stadium Field house
- Started re-roofing the entire building last week.
- Started interior renovation work in weight room.
- Timberline Elementary
- Roof is complete at the Library addition.
- Exterior masonry is now complete at Library addition.
- Windows are being installed this week.
- Overhead ductwork and electrical work at Library addition is nearing completion.
- Gyp-board framing for ceiling work at Library is on-going.
- Enrichment Center / Classroom renovation – Punchlist has been complete and issued to Hunt. Substantial Completion scheduled for the end of this week!
- CHHS Parking Lot
- Retaining wall work and some tree planting – Christmas break.
- Bid Package-3: (CMS & New CES)
- New Colleyville Elementary
- Structural Steel Erection
- Interior ductwork, electrical and steel stud partitions being installed.
- CMU exterior walls being constructed throughout.
- Face brick veneer to begin in the next two weeks.
- Roofing is scheduled to begin next week.
- Colleyville Middle
- Steel structure is complete.
- CMU walls are nearing completion at the gym area.
- Face brick veneer scheduled to start in two weeks.
- Roofing to begin in two weeks.
- Bid Package-4: (SLES & HMS)
- Heritage Middle
- All foundation grade beams are complete.
- Under floor plumbing is being worked on now.
- Floor slab work to begin in the next week.
- Silverlake Elementary
- The slab is complete!
- Structural steel erection to begin by the end of this week.
- CMU walls to start next week
|
| 11/13/06 |
An update was provided on activities related to the 2005 Bond Program. during the Board of Trustees regular monthly meeting in November. The following items were discussed:
- Bid Package 1: Football fields are complete. The infield of the CHHS baseball field has been re-graded and new sod is being installed.
- On Bid Package 2, roofing is near completion and all interior partitions are in place for the BCES classroom and cafeteria additions. At TES, exterior masonry work and interior walls are complete, and the Enrichment Center renovation is expected to be mostly complete by the first week of December. Work is scheduled to begin at CTMS and Mustang-Panther Stadium in December 2006.
- On Bid Package 3, structural steel is being installed at the new Colleyville Elementary campus as is HVAC, electrical and plumbing. At CMS, masonry walls are complete at the dressing rooms and concession area of the new gym. Work continues on structural steel and roofing.
- On Bid Package 4, all foundation piers are in place at both HMS and SLES, and under-floor plumbing is being installed. The first foundation pour for the HMS addition is set for this week.
- Projects in Bid Package 5 (BES, existing CES, GHES, OCT and GHS) are currently in the construction documents phase. The tentative bid period for these projects is January/February 2007.
|
| 10/25/06 |
An update was provided on activities related to the 2005 Bond Program.
- Bid Package 1: Football fields are complete with the exception of minor grading repairs. Work continues on the CHHS baseball field.
- On Bid Package 2, the CHHS parking lot is completed and in use, and work is set to begin this week on the marquee retaining wall. At BCES, exterior walls of the new cafeteria and classroom additions are in place and interior partitions are being constructed. Work continues on plumbing and HVAC ducts. At TES, steel framing and interior partitions are in place for the library addition and sheetrock installation begins this week. Work continues on HVAC and electrical systems. Work is scheduled to begin at CTMS in December and at Mustang-Panther Stadium in spring 2007.
- On Bid Package 3, all first-floor foundation slabs are complete for the new Colleyville Elementary campus and steel framing is underway for the administration and kindergarten areas of the building. Exterior masonry work is set to begin within the next two weeks. Fire lanes, road and parking lots are 90 percent complete. At CMS, the foundation slab for the new gymnasium is complete and masonry walls are being constructed. The existing tennis courts have been removed and the area is being prepared for installation of the new courts, which are scheduled to be complete by the end of November.
- On Bid Package 4, under-floor plumbing and storm drain lines are installed at SLES and area is being prepared at HMS to pour the slab for the additions.
- Projects in Bid Package 5 (BES, existing CES, GHES, OCT and GHS) are currently in the construction documents phase. The tentative bid period for these projects is January/February 2007.
|
|
| |
|
|
|